Westland Bunker Data Center

Westland Bunker Data Center

Concrete, Demolition, Earthwork, Underground

Scope of Work


  • Remove existing fortified bunker entrance from 15’above grade to 30’ below grade
  • 24” thick concrete structure
  • Tie into existing bunker


  • Strip site of existing vegetation and trees
  • Excavate and Stock Pile 30,000 yards of existing soils
  • Back fill basement walls and install french drain system


  • Complete storm sewer systems
  • 85’ underground bore, 19’ deep


  • 120,000 sf two building built into the side of a hill
  • 1,500 LF of 23’ tall basement walls
  • 32 spread footings
  • 37,000 sf of paving and drives

 See the expansion underway!